Fractional Durations Explained
You may have noticed in your schedule that the total float appears to be calculating incorrectly. Case and point, the image below shows the finish date is equal to the constraint date, but the total float is one day (it should be zero).When I first saw this, I used to think it was a bug in P6. I use...